Port Congestion Overview Of General Cargo Vessels In Africa ,July 2026

Jul 13, 2026

Leave a message

1, West African ports under pressure (waiting for more than 7 days for berthing)
Severe congestion

1. Conakry
    The average waiting time for scattered boats at anchor is 14-30 days, and the longest queue during peak hours for 60 days before they can dock. The equipment of Ximengdu Iron Mine is concentrated at the port, and the terminal equipment is aging, the yard is saturated, and there is a shortage of inland trailers. The unloading cycle of large items has doubled, and the demurrage and storage costs are high. Multiple shipping companies have added congestion surcharges. Alternative port: Dakar, waiting time is only 3-5 days.
2. Lagos
  The offshore queue lasts for 7-19 days, and the port area is filled with construction vehicles and infrastructure equipment. Local infrastructure goods are concentrated at the port, heavy lift berths are tight, high temperatures are reducing operating hours, and there is a shortage of inland trailer supply. After the goods arrive at the port, an additional 10 day buffer period needs to be reserved for pick-up.

Moderate congestion

1. Abidjan
The average waiting time for berthing is 7-9 days, with a yard utilization rate of over 95%. Frequent power failures slow down loading and unloading, and tight schedules for large equipment berths.
2. Tema
Waiting for more than 7 days, insufficient berth resources, low priority for steel and engineering equipment operations, and delayed berthing during peak seasons.

2, East African Port (waiting for more than 7 days)

1. BEIRA (Mozambique)
The average waiting time for anchoring in the anchorage is over 13 days, but the number of berths is insufficient. Inland transit infrastructure cargo is concentrated, and the yard is filled with large equipment, resulting in slow customs clearance speed.
2. Dar es Salaam
Scattered ships wait for 7-12 days to dock, while transit cargo from multiple inland countries in Tanzania is concentrated. The terminal lifting equipment is insufficient, and the loading and scheduling of large items is long.
3. Mombasa
Waiting for 5-12 days of floating, shortage of inland trailers, long-term occupation of storage yards by infrastructure equipment and steel, and overall extended circulation cycle.

3, Mediterranean North African Port (waiting for more than 7 days)

1. Alexandria (Egypt)
Scattered ships wait for 7-8 days to berth, and there is a scarcity of dedicated berths for heavy lifting. There is a serious queue for large-scale engineering operations, and the daily workload at the dock is limited.
2. Diliskelesi (Egypt)
Waiting for more than 7 days, with few loading and unloading stations for large equipment, and long waiting times for steel and complete sets of equipment.
3. Algiers (Algeria)
Waiting at anchor for 7-10 days, strict local customs clearance review, insufficient yard capacity, and long equipment and cargo detention period; Incomplete documents will significantly prolong the demurrage time.
4. Oran (Algeria)
Waiting for about 7 days, heavy lifting resources are tight, and the cargo for ultra long and ultra wide projects needs to be scheduled in advance.

4, Current situation of congestion at mainstream ports in the Red Sea

Jeddah (Red Sea congested area)

Line up for 15-30 days at the anchorage for scattered boats. The volume of goods diverted from the Red Sea has surged, the import of goods during the pilgrimage season has surged, the port yard is saturated by 90%, inland trailer congestion, and the customs clearance and delivery cycle for large equipment is as long as 6-8 weeks. Various storage and demurrage fees continue to rise.
Alternative transit ports: Sarala, Khorfakan, waiting for only 2-4 days, with stable delivery time.

Djibouti (transit hub)

Mild congestion, waiting for 3-6 days for parking, not reaching the 7-day warning line, only for diversion reference.

5,General Shipping Guidelines for Africa Exports

1. The rainy season in West Africa coincides with high temperatures, cutting daily terminal working hours by 30%, and sailing schedules are generally delayed by 10–25 days.
2. Prioritize transshipment ports for extra-long, extra-wide and overweight oversize cargoes; direct berthing at Conakry and Lagos will most likely incur exorbitant demurrage fees.
3. Complete ECTN/BESC documentation prior to shipment. Missing certificates will lead to cargo detention and further delivery delays.

6,Shipping Risk Avoidance Advice

  Reserve a 20–30 day buffer period during booking to cover unexpected delays caused by berthing waits, customs clearance and inland transit.

   Noted:The stated port congestion durations reflect normal conditions in July. Waiting times will be dynamically extended due to terminal maintenance, policy adjustments or severe weather. Sufficient buffer time is strongly recommended for all shipments.
 